The final order must give effect to the lawful public purpose and the remedy

The Supreme Court set aside the Division Bench’s judgment. The Single Judge’s order was restored. The original amount was ordered refunded with seven per cent interest. Any outstanding interest balance was payable within three months. The plot was barred from commercial use. It had to be used for education and incidental activities. These directions resolved both the allottee’s monetary claim and the land’s intended use. The appeals were allowed. Bihar Industrial Area Development Authority & Ors. v. M/s Scope Sales Pvt. Ltd. & Anr. | 2026 INSC 89